B 101 – surface renewal – Luckenwalde bypass
Three kilometres, approx. 51,400 m²

Client
Landesbetrieb Straßenwesen Brandenburg
Project volume
EUR 1.16 million
Construction time
03/2018 – 04/2018
The B 101, Luckenwalde bypass, was renewed over a length of more than 3 kilometres. Approx. 51,400 m² of asphalt surface course and asphalt binder course were milled out of the road.
The road was reconstructed with 51,400 m² of asphalt binder course and 51,400 m² of stone mastic asphalt.
Approx. 19,000 m of road markings were also replaced.